Underground access

Our client was conducting a multi-million pound refurbishment of an underground tunnel. They needed a powered access solution that would enable them to work at height, would be free from fluid spills and could be operated 24 hours a day, 7 days a week. The client had already been supplied with powered access, but it had been removed after a poor health and safety performance.

We visited the site and conducted a full survey, and agreed a 24/7 service level which included daily toolbox talks and operative training.

“We could afford very little downtime on this project, and we had already used up the little leeway we had. So, it was imperative that we chose suppliers that could give us a uptime guarantee. 2Rent were great. Not only was the access platform a well-maintained piece of equipment, they were on hand to sort out any issues as and when”